Rafinery

STAR Rafineri – TSGI / Aliağa 2015 – On Going

Electromechanical and Steel Structure Erection – P3 & P5

STAR Rafineri – TSGI / Aliağa 2014

EPC Tank Farm Project of Star, consisting of 23 storage tanks with a total capacity of 320.000 m³.

TÜPRAŞ / Körfez 2014 - 2015

RUP Project Railcar Unloading Unit

STAR / Aliağa 2012 - 2014

Engineering, Supply and Installation of Three New Naphta Tanks

TÜPRAŞ - Tecnicas Reunidas / Yarımca, 2012 - 2015

EPC tank farm project of RUP consisting of 18 storage tanks with a total capacity of 600.000 m³.

SHELL / Derince 2011

Cylindrical storage tanks.

TÜPRAŞ / Aliağa 2010

Metering system project.

TÜPRAŞ / Körfez 2009-2010

Civil & elecro - mechanical & automation of land-side filling terminals

TOTAL - SADAŞ / Samsun 2008-2010

Terminal expansion project (4x4200 m3 + 4x520 m3 cylindirical tank installation and addtive injection system)

TÜPRAŞ / Körfez 2008

Civil & electro-mechanical construction of product biending unit

TÜPRAŞ / Körfez 2006

Renovation and piping of Korfez Tank Farm (4X75.000 m3 aluminium floating & conical roof)

POAŞ / Trabzon 2005-2006

Terminal modernization

POAŞ / Antalya 2002

Cylindirical storage tank farm. (22 pcs. of tanks with total capacity 70.000 m3)